There is no doubt that the IT examination plays an essential role in the IT field. On the one hand, there is no denying that the Construction-Manager practice exam materials provides us with a convenient and efficient way to measure IT workers' knowledge and ability(Construction-Manager best questions). On the other hand, up to now, no other methods have been discovered to replace the examination. That is to say, the IT examination is still regarded as the only reliable and feasible method which we can take (Construction-Manager certification training), and other methods are too time- consuming and therefore they are infeasible, thus it is inevitable for IT workers to take part in the IT exam. However, how to pass the CMAA Construction-Manager exam has become a big challenge for many people and if you are one of those who are worried, congratulations, you have clicked into the right place--Construction-Manager practice exam materials. Our company is committed to help you pass exam and get the IT certification easily. Our company has carried out cooperation with a lot of top IT experts in many countries to compile the Construction-Manager best questions for IT workers and our exam preparation are famous for their high quality and favorable prices. The shining points of our Construction-Manager certification training files are as follows.

Fast delivery in 5 to 10 minutes after payment
Our company knows that time is precious especially for those who are preparing for CMAA Construction-Manager exam, just like the old saying goes "Time flies like an arrow, and time lost never returns." We have tried our best to provide our customers the fastest delivery. We can ensure you that you will receive our Construction-Manager practice exam materials within 5 to 10 minutes after payment, this marks the fastest delivery speed in this field. Therefore, you will have more time to prepare for the Construction-Manager actual exam. Our operation system will send the Construction-Manager best questions to the e-mail address you used for payment, and all you need to do is just waiting for a while then check your mailbox.
Simulate the real exam
We provide different versions of Construction-Manager practice exam materials for our customers, among which the software version can stimulate the real exam for you but it only can be used in the windows operation system. It tries to simulate the Construction-Manager best questions for our customers to learn and test at the same time and it has been proved to be good environment for IT workers to find deficiencies of their knowledge in the course of stimulation.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Only need to practice for 20 to 30 hours
You will get to know the valuable exam tips and the latest question types in our Construction-Manager certification training files, and there are special explanations for some difficult questions, which can help you to have a better understanding of the difficult questions. All of the questions we listed in our Construction-Manager practice exam materials are the key points for the IT exam, and there is no doubt that you can practice all of Construction-Manager best questions within 20 to 30 hours, even though the time you spend on it is very short, however the contents you have practiced are the quintessence for the IT exam. And of course, if you still have any misgivings, you can practice our Construction-Manager certification training files again and again, which may help you to get the highest score in the IT exam.
CMAA Certified Construction Manager (CCM) Sample Questions:
1. A CM team on a new project which is in the pre-design phase is planning their climate resiliency strategy.
Which of the following is the team's BEST first step in this process?
A) Hire a commissioning agent.
B) Establish QA/QC specifications.
C) Establish a third-party certification.
D) Collect relevant data and reports.
2. Under the Brooks Act, professional services of architects and engineers on federal projects must be
A) audited every six months.
B) contracted before GC services.
C) funded by public dollars.
D) qualification-based rather than bid.
3. As the owner's representative, you are providing on-site construction management services to a municipality for their new design-build city hall project.
The mechanical subcontractor discovers that his ductwork will not fit in the above-ceiling area of the Mayor's office. Which entity is best-suited to resolve this risk?
A) Architect (DOR)
B) Owner (Municipality)
C) Design-Build Team
D) Owner's rep
4. Float, date, and duration are examples of
A) logic elements.
B) schedule elements.
C) schedule parameters.
D) constraints.
5. A construction manager is responsible for the bid review and evaluation of an $85 million high school project.
All bids must be submitted in person at the client's Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?
A) Send the bid back to the contractor and apologize for the mishap.
B) Put the contractor's unopened bid in tight security until the bid opening has been completed.
C) Include the unopened bid. since it clearly was an oversight.
D) Inform the Owner and review the instructions to bidders for guidance on how to proceed.
Solutions:
| Question # 1 Answer: D | Question # 2 Answer: D | Question # 3 Answer: C | Question # 4 Answer: C | Question # 5 Answer: D |