There is no doubt that the IT examination plays an essential role in the IT field. On the one hand, there is no denying that the 70-178 practice exam materials provides us with a convenient and efficient way to measure IT workers' knowledge and ability(70-178 best questions). On the other hand, up to now, no other methods have been discovered to replace the examination. That is to say, the IT examination is still regarded as the only reliable and feasible method which we can take (70-178 certification training), and other methods are too time- consuming and therefore they are infeasible, thus it is inevitable for IT workers to take part in the IT exam. However, how to pass the Microsoft 70-178 exam has become a big challenge for many people and if you are one of those who are worried, congratulations, you have clicked into the right place--70-178 practice exam materials. Our company is committed to help you pass exam and get the IT certification easily. Our company has carried out cooperation with a lot of top IT experts in many countries to compile the 70-178 best questions for IT workers and our exam preparation are famous for their high quality and favorable prices. The shining points of our 70-178 certification training files are as follows.
Simulate the real exam
We provide different versions of 70-178 practice exam materials for our customers, among which the software version can stimulate the real exam for you but it only can be used in the windows operation system. It tries to simulate the 70-178 best questions for our customers to learn and test at the same time and it has been proved to be good environment for IT workers to find deficiencies of their knowledge in the course of stimulation.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Fast delivery in 5 to 10 minutes after payment
Our company knows that time is precious especially for those who are preparing for Microsoft 70-178 exam, just like the old saying goes "Time flies like an arrow, and time lost never returns." We have tried our best to provide our customers the fastest delivery. We can ensure you that you will receive our 70-178 practice exam materials within 5 to 10 minutes after payment, this marks the fastest delivery speed in this field. Therefore, you will have more time to prepare for the 70-178 actual exam. Our operation system will send the 70-178 best questions to the e-mail address you used for payment, and all you need to do is just waiting for a while then check your mailbox.
Only need to practice for 20 to 30 hours
You will get to know the valuable exam tips and the latest question types in our 70-178 certification training files, and there are special explanations for some difficult questions, which can help you to have a better understanding of the difficult questions. All of the questions we listed in our 70-178 practice exam materials are the key points for the IT exam, and there is no doubt that you can practice all of 70-178 best questions within 20 to 30 hours, even though the time you spend on it is very short, however the contents you have practiced are the quintessence for the IT exam. And of course, if you still have any misgivings, you can practice our 70-178 certification training files again and again, which may help you to get the highest score in the IT exam.
Microsoft Project 2010, Managing Projects Sample Questions:
1. The milestones in your project schedule represent the end of phases. You need to change the background color of the cells of the milestones to blue. What should you do on the Format tab?
A) Select Text Styles, and then select Milestone Tasks.
B) Select Column Settings, and then select Milestone.
C) Select Layout, and then select Show drawings.
D) Select Bar Styles, and then select Milestone.
E) Select Drawing, and then select Text Box.
2. You need to ensure that you can view only the tasks on your projects critical path. What should you do?
A) On the Advanced tab of the Project 2010 options, select the Calculate multiple critical paths check box.
B) On the Advanced tab of the Project 2010 options, modify the Tasks are critical if slack is less than or equal to option.
C) View the projects Gantt chart and apply the Critical group.
D) View the project's Gantt chart and apply the Critical filter.
3. You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?
A) Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.
B) Highlight the summary task. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.
C) Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, and then click OK.
D) Highlight the summary task. Click Set Baseline and select Baseline1.Click the Entire Project radio button, and then click OK.
4. Your project schedule contains both Work and Material resources. The resources are assigned to tasks and are of either the committed or proposed booking type. You need to ensure that the project does not contain over-allocated resources. Which feature should you use?
A) Clear Leveling
B) Assign Resources
C) Level All
D) Resource Pool C Share Resources
5. You need to set the default constraint type for all new tasks to As Late As Possible. What should you do?
A) Select all tasks, and then set the constraint type to As Late As Possible.
B) Select all tasks, and then click Layout.
C) In the Project Information window, from the Schedule From drop-down list box, select Project Finish Date.
D) In the Options dialog box, enable the New Tasks are effort driven check box.
Solutions:
Question # 1 Answer: A | Question # 2 Answer: D | Question # 3 Answer: B | Question # 4 Answer: C | Question # 5 Answer: C |