Simulate the real exam
We provide different versions of 70-178 practice exam materials for our customers, among which the software version can stimulate the real exam for you but it only can be used in the windows operation system. It tries to simulate the 70-178 best questions for our customers to learn and test at the same time and it has been proved to be good environment for IT workers to find deficiencies of their knowledge in the course of stimulation.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Fast delivery in 5 to 10 minutes after payment
Our company knows that time is precious especially for those who are preparing for Microsoft 70-178 exam, just like the old saying goes "Time flies like an arrow, and time lost never returns." We have tried our best to provide our customers the fastest delivery. We can ensure you that you will receive our 70-178 practice exam materials within 5 to 10 minutes after payment, this marks the fastest delivery speed in this field. Therefore, you will have more time to prepare for the 70-178 actual exam. Our operation system will send the 70-178 best questions to the e-mail address you used for payment, and all you need to do is just waiting for a while then check your mailbox.
There is no doubt that the IT examination plays an essential role in the IT field. On the one hand, there is no denying that the 70-178 practice exam materials provides us with a convenient and efficient way to measure IT workers' knowledge and ability(70-178 best questions). On the other hand, up to now, no other methods have been discovered to replace the examination. That is to say, the IT examination is still regarded as the only reliable and feasible method which we can take (70-178 certification training), and other methods are too time- consuming and therefore they are infeasible, thus it is inevitable for IT workers to take part in the IT exam. However, how to pass the Microsoft 70-178 exam has become a big challenge for many people and if you are one of those who are worried, congratulations, you have clicked into the right place--70-178 practice exam materials. Our company is committed to help you pass exam and get the IT certification easily. Our company has carried out cooperation with a lot of top IT experts in many countries to compile the 70-178 best questions for IT workers and our exam preparation are famous for their high quality and favorable prices. The shining points of our 70-178 certification training files are as follows.
Only need to practice for 20 to 30 hours
You will get to know the valuable exam tips and the latest question types in our 70-178 certification training files, and there are special explanations for some difficult questions, which can help you to have a better understanding of the difficult questions. All of the questions we listed in our 70-178 practice exam materials are the key points for the IT exam, and there is no doubt that you can practice all of 70-178 best questions within 20 to 30 hours, even though the time you spend on it is very short, however the contents you have practiced are the quintessence for the IT exam. And of course, if you still have any misgivings, you can practice our 70-178 certification training files again and again, which may help you to get the highest score in the IT exam.
Microsoft Project 2010, Managing Projects Sample Questions:
1. You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?
A) Remove the predecessor assignments.
B) Change Work to zero hours.
C) Click the Insert Milestone button.
D) Select the Mark Task as Milestone check box.
2. You manage a project that specifies all constraint types to As Soon As Possible. You discover that one of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted finish date on the default Gantt chart. What should you modify in the Task Information window?
A) Select the Display on Timeline check box.
B) Select the Mark task as milestone check box.
C) Set the Deadline date field.
D) Set the Finish date field.
E) Set the Constraint date field.
3. You have a project schedule in progress. You need to view only the tasks that currently affect the overall completion date. What should you do in the Gantt Chart view?
A) Apply the Critical Tasks filter.
B) Apply the Status group.
C) Apply the Late Tasks filter.
D) Apply the Incomplete Tasks filter.
E) Apply the Priority group.
4. Your project has some resources with rates that adjust over time. You need to ensure that project costs automatically adjust for these resources. What should you do?
A) Change the resource availability settings to establish Units for selected dates.
B) Create resources that include fixed Standard costs, and then apply a rate variance per project task.
C) Create cost tables to include rates that activate on effective dates.
D) Create a named resource for each Standard hourly rate.
5. All tasks in your project use the Auto Schedule mode. Several tasks are in progress. You need to reschedule all the remaining work on the project. You also need to achieve this goal without having rigid constraints set to your project's tasks. What should you do?
A) Change the Status Date field.
B) Click Calculate Project.
C) Click Update Project.
D) Click Move Project.
Solutions:
Question # 1 Answer: D | Question # 2 Answer: C | Question # 3 Answer: A | Question # 4 Answer: C | Question # 5 Answer: C |