Free demo before buying
We are so proud of high quality of our 70-178 exam simulation: Microsoft Project 2010, Managing Projects, and we would like to invite you to have a try, so please feel free to download the free demo in the website, we firmly believe that you will be attracted by the useful contents in our 70-178 study guide materials. There are all essences for the IT exam in our Microsoft Project 2010, Managing Projects exam questions, which can definitely help you to passed the IT exam and get the IT certification easily.
No help, full refund
Our company is committed to help all of our customers to pass Microsoft 70-178 as well as obtaining the IT certification successfully, but if you fail exam unfortunately, we will promise you full refund on condition that you show your failed report card to us. In the matter of fact, from the feedbacks of our customers the pass rate has reached 98% to 100%, so you really don't need to worry about that. Our 70-178 exam simulation: Microsoft Project 2010, Managing Projects sell well in many countries and enjoy high reputation in the world market, so you have every reason to believe that our 70-178 study guide materials will help you a lot.
We believe that you can tell from our attitudes towards full refund that how confident we are about our products. Therefore, there will be no risk of your property for you to choose our 70-178 exam simulation: Microsoft Project 2010, Managing Projects, and our company will definitely guarantee your success as long as you practice all of the questions in our 70-178 study guide materials. Facts speak louder than words, our exam preparations are really worth of your attention, you might as well have a try.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Under the situation of economic globalization, it is no denying that the competition among all kinds of industries have become increasingly intensified (70-178 exam simulation: Microsoft Project 2010, Managing Projects), especially the IT industry, there are more and more IT workers all over the world, and the professional knowledge of IT industry is changing with each passing day. Under the circumstances, it is really necessary for you to take part in the Microsoft 70-178 exam and try your best to get the IT certification, but there are only a few study materials for the IT exam, which makes the exam much harder for IT workers. Now, here comes the good news for you. Our company has committed to compile the 70-178 study guide materials for IT workers during the 10 years, and we have achieved a lot, we are happy to share our fruits with you in here.
Convenience for reading and printing
In our website, there are three versions of 70-178 exam simulation: Microsoft Project 2010, Managing Projects for you to choose from namely, PDF Version, PC version and APP version, you can choose to download any one of 70-178 study guide materials as you like. Just as you know, the PDF version is convenient for you to read and print, since all of the useful study resources for IT exam are included in our Microsoft Project 2010, Managing Projects exam preparation, we ensure that you can pass the IT exam and get the IT certification successfully with the help of our 70-178 practice questions.
Microsoft Project 2010, Managing Projects Sample Questions:
1. You create a custom Timeline view of summary tasks and key milestones. You need to send an image of only the custom Timeline view by e-mail. Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)
A) Copy and paste the Timeline view into the body of the e-mail.
B) On the Format tab, select Copy Timeline, and then click For email.
C) On the File menu, select Save & Send, and then click Create a PDF/XPS Document.
D) On the File menu, select Save & Send, and then click Send as Attachment.
2. One of your tasks in your project plan is 50 percent complete. The task has a finish variance of 4 days and a work variance of -14 days. Which set of values describes the task?
A) The task is early by 4 days.
B) The task is early by 14 days.
C) The task is late by 14 days.
D) The task is late by 4 days.
3. You receive approval for a project plan that is yet to start. You need to ensure that all project tasks start no earlier than September 13, 2010. Which project level field should you set?
A) Change the calendar type in the Project Options dialog box.
B) Change the Status Date field to 9/13/2010.
C) In the Start Date field, type 9/13/2010.
D) In the Current Date field, type 9/13/2010.
4. Your customer wants to receive your project's Timeline view in a document by e-mail. You need to create a document that contains only the Timeline view. You select the Timeline view. What should you do next?
A) Select Save View.
B) Select Visual Reports.
C) Select Create PDF/XPS Document.
D) Select Sync With Task List.
5. You have added two new tasks to your project. Both tasks are subtasks to a summary task. You need to update Baseline1 only for the two new tasks. What should you do?
A) Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.
B) Highlight the summary task. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, select To all summary tasks, and then click OK.
C) Highlight the two tasks. Click Set Baseline and select Baseline1.Click the Selected Tasks radio button, and then click OK.
D) Highlight the summary task. Click Set Baseline and select Baseline1.Click the Entire Project radio button, and then click OK.
Solutions:
Question # 1 Answer: C,D | Question # 2 Answer: D | Question # 3 Answer: C | Question # 4 Answer: B | Question # 5 Answer: B |