There is no doubt that the IT examination plays an essential role in the IT field. On the one hand, there is no denying that the CCM practice exam materials provides us with a convenient and efficient way to measure IT workers' knowledge and ability(CCM best questions). On the other hand, up to now, no other methods have been discovered to replace the examination. That is to say, the IT examination is still regarded as the only reliable and feasible method which we can take (CCM certification training), and other methods are too time- consuming and therefore they are infeasible, thus it is inevitable for IT workers to take part in the IT exam. However, how to pass the Medical Professional CCM exam has become a big challenge for many people and if you are one of those who are worried, congratulations, you have clicked into the right place--CCM practice exam materials. Our company is committed to help you pass exam and get the IT certification easily. Our company has carried out cooperation with a lot of top IT experts in many countries to compile the CCM best questions for IT workers and our exam preparation are famous for their high quality and favorable prices. The shining points of our CCM certification training files are as follows.
Simulate the real exam
We provide different versions of CCM practice exam materials for our customers, among which the software version can stimulate the real exam for you but it only can be used in the windows operation system. It tries to simulate the CCM best questions for our customers to learn and test at the same time and it has been proved to be good environment for IT workers to find deficiencies of their knowledge in the course of stimulation.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Fast delivery in 5 to 10 minutes after payment
Our company knows that time is precious especially for those who are preparing for Medical Professional CCM exam, just like the old saying goes "Time flies like an arrow, and time lost never returns." We have tried our best to provide our customers the fastest delivery. We can ensure you that you will receive our CCM practice exam materials within 5 to 10 minutes after payment, this marks the fastest delivery speed in this field. Therefore, you will have more time to prepare for the CCM actual exam. Our operation system will send the CCM best questions to the e-mail address you used for payment, and all you need to do is just waiting for a while then check your mailbox.
Only need to practice for 20 to 30 hours
You will get to know the valuable exam tips and the latest question types in our CCM certification training files, and there are special explanations for some difficult questions, which can help you to have a better understanding of the difficult questions. All of the questions we listed in our CCM practice exam materials are the key points for the IT exam, and there is no doubt that you can practice all of CCM best questions within 20 to 30 hours, even though the time you spend on it is very short, however the contents you have practiced are the quintessence for the IT exam. And of course, if you still have any misgivings, you can practice our CCM certification training files again and again, which may help you to get the highest score in the IT exam.
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions:
1. Which of the following situations form legally binding contracts? (2 correct answers apply) Choose all of the correct answers (multiple possibilities)
A) The Employer received the Contractor's Letter of Tender and issued a conditional Letter of Acceptance.
B) The Employer and the Contractor signed the Contract Agreement.
C) The Employer received the Contractor's Letter of Tender and issued a Letter of Intent.
D) The Employer received the Contractor's Letter of Tender and issued Letter of Acceptance.
2. You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?
A) The Engineer requests a proposal regarding a change in type of windows and doors of the business centre.
B) The Contractor submits a Value Engineering proposal, in which it proposed to change the colour of the outdoor paint. The Engineer approved the proposal.
C) The Engineer instructs a change in slopes of stairs to the parking lot with an Instruction in accordance with Sub-Clause 3.3.
D) The Employer verbally instructs a change in the layout of the rooftop restaurant. The Engineer issued an Instruction describing the required change with revised design drawings.
3. Which one of the following statements is NOT correct in respect of FIDIC Red Book (both editions)?
A) The Contract is administered by the Engineer who is appointed by the Employer. If disputes arise, they are referred to a Dispute Adjudication Board (DAB) for its decisions.
B) The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.
C) The General Conditions allocate the risks between the parties on a fair and equitable basis.
D) The Letter of Tender may be worded by the Contractor (at its discretion) so as to allow for the alternative of the Contract to become effective when the Employer issues a Letter of Acceptance.
4. Which of the following statements are not correct?
Choose all of the correct answers (multiple possibilities).
A) The Engineer shall keep records of the Progress Meetings.
B) Only the Engineer can call for a meeting
C) Subcontractors cannot attend management or progress meetings unless the Engineer's approval is obtained.
D) The Contractor or the Engineer can request a meeting.
E) Only the Employer can call for a meeting.
5. You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition
2017), with Time for Completion of 5 months.
The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
What is the correct Commencement Date?
A) 1 August 2022
B) 15 June 2022
C) 15 July 2022
D) 12 June 2022
Solutions:
Question # 1 Answer: B,D | Question # 2 Answer: B | Question # 3 Answer: D | Question # 4 Answer: B,E | Question # 5 Answer: A |