Convenience for reading and printing
In our website, there are three versions of CCM exam simulation: Certified Case Manager Certification Exam (CCM) for you to choose from namely, PDF Version, PC version and APP version, you can choose to download any one of CCM study guide materials as you like. Just as you know, the PDF version is convenient for you to read and print, since all of the useful study resources for IT exam are included in our Certified Case Manager Certification Exam (CCM) exam preparation, we ensure that you can pass the IT exam and get the IT certification successfully with the help of our CCM practice questions.
Free demo before buying
We are so proud of high quality of our CCM exam simulation: Certified Case Manager Certification Exam (CCM), and we would like to invite you to have a try, so please feel free to download the free demo in the website, we firmly believe that you will be attracted by the useful contents in our CCM study guide materials. There are all essences for the IT exam in our Certified Case Manager Certification Exam (CCM) exam questions, which can definitely help you to passed the IT exam and get the IT certification easily.
No help, full refund
Our company is committed to help all of our customers to pass Medical Professional CCM as well as obtaining the IT certification successfully, but if you fail exam unfortunately, we will promise you full refund on condition that you show your failed report card to us. In the matter of fact, from the feedbacks of our customers the pass rate has reached 98% to 100%, so you really don't need to worry about that. Our CCM exam simulation: Certified Case Manager Certification Exam (CCM) sell well in many countries and enjoy high reputation in the world market, so you have every reason to believe that our CCM study guide materials will help you a lot.
We believe that you can tell from our attitudes towards full refund that how confident we are about our products. Therefore, there will be no risk of your property for you to choose our CCM exam simulation: Certified Case Manager Certification Exam (CCM), and our company will definitely guarantee your success as long as you practice all of the questions in our CCM study guide materials. Facts speak louder than words, our exam preparations are really worth of your attention, you might as well have a try.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Under the situation of economic globalization, it is no denying that the competition among all kinds of industries have become increasingly intensified (CCM exam simulation: Certified Case Manager Certification Exam (CCM)), especially the IT industry, there are more and more IT workers all over the world, and the professional knowledge of IT industry is changing with each passing day. Under the circumstances, it is really necessary for you to take part in the Medical Professional CCM exam and try your best to get the IT certification, but there are only a few study materials for the IT exam, which makes the exam much harder for IT workers. Now, here comes the good news for you. Our company has committed to compile the CCM study guide materials for IT workers during the 10 years, and we have achieved a lot, we are happy to share our fruits with you in here.
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions:
1. The Contractor is entitled to an advance payment. Applying FIDIC Red Book (edition 1999), which two of the following statements are correct?
Choose all of the correct answers (multiple possibilities):
A) Under the General Conditions, the advance payment will be repaid by deducting all amounts from invoices until the entire advance payment is repaid.
B) Under the General Conditions, the amount of advance payment is to be paid in full by the Employer through one instalment.
C) The advance payment reflects the amount of works the Contractor has already performed up to the moment such advance payment is performed.
D) The advance payment is to help the Contractor to finance some of its early cost and expenditure until it becomes entitled to first (non-interim) payment.
2. You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition
2017). The project had been suspended due to a material change in the Employer's financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?
A) A prolonged suspension for more than 1 year has affected the whole of the Works.
B) The Contractor has requested the Employer but has not received any evidence that the financial arrangement is being maintained, despite having sent a notice thereto 4 months earlier.
C) The Contractor does not receive the amount due under the latest Payment Certificate for more than 4 months after the due date.
D) The Employer failed to comply with a final and binding determination issued by the Engineer, and such failure constitutes a material breach of the Employer's obligations under the Contract.
3. Which of the following obligations are relevant to the Engineer's roles with regards to insurance? [2017 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
A) The Engineer shall immediately suspend all construction activities at the Site, in case the Contractor failed to take out any necessary insurance.
B) The Engineer should continuously monitor that the Contractor's insurance policies are kept valid, and extensions are duly arranged, when necessary.
C) The Engineer shall receive a copy of the evidence(s) demonstrating Contractor's payment of the necessary insurance premiums.
D) The Engineer is entitled to take out an insurance on behalf of the Contractor, in case the Contractor fails to extend the validity of a specific insurance.
4. What does discharge confirm under the FIDIC Red Book (edition 1999)?
A) It confirms interim settlement of all money due to the Contractor
B) It confirms the immediate end to the Contract unconditionally whenever issued.
C) None of the above three statements is correct.
D) It confirms full and final settlement of all money due to the Contractor.
5. Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?
A) A disproportionate amount of risks is allocated to the Contractor under the General Conditions.
B) The Contractor provides plant and designs (except as otherwise specified) and executes the other works, all in accordance with the Contract, which includes its Proposal and the Employer's Requirements.
C) The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.
D) The General Conditions allocate the risks between the parties on a fair and equitable basis.
Solutions:
Question # 1 Answer: A,D | Question # 2 Answer: B | Question # 3 Answer: B,C | Question # 4 Answer: D | Question # 5 Answer: A |