Convenience for reading and printing
In our website, there are three versions of CCM exam simulation: Certified Case Manager Certification Exam (CCM) for you to choose from namely, PDF Version, PC version and APP version, you can choose to download any one of CCM study guide materials as you like. Just as you know, the PDF version is convenient for you to read and print, since all of the useful study resources for IT exam are included in our Certified Case Manager Certification Exam (CCM) exam preparation, we ensure that you can pass the IT exam and get the IT certification successfully with the help of our CCM practice questions.
Free demo before buying
We are so proud of high quality of our CCM exam simulation: Certified Case Manager Certification Exam (CCM), and we would like to invite you to have a try, so please feel free to download the free demo in the website, we firmly believe that you will be attracted by the useful contents in our CCM study guide materials. There are all essences for the IT exam in our Certified Case Manager Certification Exam (CCM) exam questions, which can definitely help you to passed the IT exam and get the IT certification easily.
No help, full refund
Our company is committed to help all of our customers to pass Medical Professional CCM as well as obtaining the IT certification successfully, but if you fail exam unfortunately, we will promise you full refund on condition that you show your failed report card to us. In the matter of fact, from the feedbacks of our customers the pass rate has reached 98% to 100%, so you really don't need to worry about that. Our CCM exam simulation: Certified Case Manager Certification Exam (CCM) sell well in many countries and enjoy high reputation in the world market, so you have every reason to believe that our CCM study guide materials will help you a lot.
We believe that you can tell from our attitudes towards full refund that how confident we are about our products. Therefore, there will be no risk of your property for you to choose our CCM exam simulation: Certified Case Manager Certification Exam (CCM), and our company will definitely guarantee your success as long as you practice all of the questions in our CCM study guide materials. Facts speak louder than words, our exam preparations are really worth of your attention, you might as well have a try.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Under the situation of economic globalization, it is no denying that the competition among all kinds of industries have become increasingly intensified (CCM exam simulation: Certified Case Manager Certification Exam (CCM)), especially the IT industry, there are more and more IT workers all over the world, and the professional knowledge of IT industry is changing with each passing day. Under the circumstances, it is really necessary for you to take part in the Medical Professional CCM exam and try your best to get the IT certification, but there are only a few study materials for the IT exam, which makes the exam much harder for IT workers. Now, here comes the good news for you. Our company has committed to compile the CCM study guide materials for IT workers during the 10 years, and we have achieved a lot, we are happy to share our fruits with you in here.
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions:
1. Regarding the FIDIC Red Book (edition 1999): which two statements are true in respect of Building Information Modelling (BIM)?
Choose all of the correct answers (multiple possibilities).
A) General Conditions of Contract require the use of BIM.
B) For construction or building projects involving BIM, many Sub-Clauses of FIDIC Red Book (edition
2017) should be thoroughly reviewed when drafting the Particular Conditions.
C) BIM is one of the digital data technologies used in all aspects of project planning, investigation, design, construction and operation.
D) BIM is not related to the improvement of quality, accuracy, delivery times and cost savings.
2. You are the Contract Manager of the Contractor in a building project. The Contract has been awarded to your firm, but the Engineer has not been selected. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, which must be done within 14 days after the signing of the Contract Agreement. The Employer requested your firm to commence works on the 14th day after signing the Contract Agreement. Your director, Y, wants to wait with commencing the works until the Engineer has been selected or until the 42 days since the date your firm receives Letter of Acceptance. Is Y correct?
A) Yes
B) No
3. The amount of an advance payment guarantee provided for pursuant to FIDIC Red and Yellow Books (both editions) may be reduced as of:
A) The date on which the entire advance payment is repaid as stated in the Payment Certificate
B) The date of the Taking Over Certificate
C) The date on which an amount is repaid by the Contractor as stated in the Payment Certificates
D) The Commencement Date
4. Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?
A) A Programme for execution of the varied work.
B) A description of the varied work.
C) Details of the resources and methods to be adopted by the Contractor.
D) A description of the proposed design.
5. Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
A) The Contractor abandons the Works and the Employer did not issue Notice of termination.
B) The Contractor failed to extend the validity of the Performance Security.
C) The Engineer had issued instruction to replace part of the Works.
D) The Contractor failed to renew the Tender Security.
E) The Employer had submitted a claim under Sub-Clause 20.2.
Solutions:
Question # 1 Answer: B,C | Question # 2 Answer: B | Question # 3 Answer: C | Question # 4 Answer: D | Question # 5 Answer: B,D |