Convenience for reading and printing
In our website, there are three versions of 070-178 exam simulation: Microsoft Project 2010, Managing Projects for you to choose from namely, PDF Version, PC version and APP version, you can choose to download any one of 070-178 study guide materials as you like. Just as you know, the PDF version is convenient for you to read and print, since all of the useful study resources for IT exam are included in our Microsoft Project 2010, Managing Projects exam preparation, we ensure that you can pass the IT exam and get the IT certification successfully with the help of our 070-178 practice questions.
Under the situation of economic globalization, it is no denying that the competition among all kinds of industries have become increasingly intensified (070-178 exam simulation: Microsoft Project 2010, Managing Projects), especially the IT industry, there are more and more IT workers all over the world, and the professional knowledge of IT industry is changing with each passing day. Under the circumstances, it is really necessary for you to take part in the Microsoft 070-178 exam and try your best to get the IT certification, but there are only a few study materials for the IT exam, which makes the exam much harder for IT workers. Now, here comes the good news for you. Our company has committed to compile the 070-178 study guide materials for IT workers during the 10 years, and we have achieved a lot, we are happy to share our fruits with you in here.
Free demo before buying
We are so proud of high quality of our 070-178 exam simulation: Microsoft Project 2010, Managing Projects, and we would like to invite you to have a try, so please feel free to download the free demo in the website, we firmly believe that you will be attracted by the useful contents in our 070-178 study guide materials. There are all essences for the IT exam in our Microsoft Project 2010, Managing Projects exam questions, which can definitely help you to passed the IT exam and get the IT certification easily.
No help, full refund
Our company is committed to help all of our customers to pass Microsoft 070-178 as well as obtaining the IT certification successfully, but if you fail exam unfortunately, we will promise you full refund on condition that you show your failed report card to us. In the matter of fact, from the feedbacks of our customers the pass rate has reached 98% to 100%, so you really don't need to worry about that. Our 070-178 exam simulation: Microsoft Project 2010, Managing Projects sell well in many countries and enjoy high reputation in the world market, so you have every reason to believe that our 070-178 study guide materials will help you a lot.
We believe that you can tell from our attitudes towards full refund that how confident we are about our products. Therefore, there will be no risk of your property for you to choose our 070-178 exam simulation: Microsoft Project 2010, Managing Projects, and our company will definitely guarantee your success as long as you practice all of the questions in our 070-178 study guide materials. Facts speak louder than words, our exam preparations are really worth of your attention, you might as well have a try.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Microsoft Project 2010, Managing Projects Sample Questions:
1. Five resources work full time on the project. Standard working hours are eight hours a day from Monday through Friday. John, a team member, asks to take Thursday off from work. He will work on Saturday to adjust this time. You need to ensure that the change in John's working time is reflected in the project schedule. What should you do?
A) In the Resource Information window for John, change John's availability by modifying the Available From and Available To dates for Thursday to 0 percent and for Saturday to 100 percent.
B) Update the project calendar for John by making Thursday as a non-working day and Saturday as a working day.
C) In the Resource Information window for John, select the inactive option for Thursday and cancel the selection of the inactive option for Saturday.
D) Update the resource calendar for John by making Thursday as a non-working day and Saturday as a working day.
2. Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
A) Change the working time for the resource.
B) Update the base project calendar.
C) Assign the resource only to tasks that are scheduled on the working days.
D) Change the maximum units for the resource.
3. You need to ensure that you can view only the tasks on your projects critical path. What should you do?
A) On the Advanced tab of the Project 2010 options, select the Calculate multiple critical paths check box.
B) On the Advanced tab of the Project 2010 options, modify the Tasks are critical if slack is less than or equal to option.
C) View the projects Gantt chart and apply the Critical group.
D) View the project's Gantt chart and apply the Critical filter.
4. The project you manage has only part-time resources. The part-time resources work four hours a day from Wednesday through Saturday. You need to create a new calendar and set the calendar as the default for your project. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A) Set the calendar type to part-time for all tasks.
B) Select the part-time calendar from the Change Working Time window.
C) Select the part-time calendar from the Project Information window.
D) Change the Calendar type in the Project Options dialog box.
E) On the Project tab, Select Change Working Time, and then click Create New Calendar.
5. The red person icon is displayed next to one of your tasks. You need to find out the reason for the display of the icon. What should you do?
A) Use the Task Inspector tool.
B) Use the Level Resource feature.
C) Display the task details.
D) View the task information.
Solutions:
Question # 1 Answer: D | Question # 2 Answer: A | Question # 3 Answer: D | Question # 4 Answer: C,E | Question # 5 Answer: A |