Convenience for reading and printing
In our website, there are three versions of C_TSCM42_64 exam simulation: SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 for you to choose from namely, PDF Version, PC version and APP version, you can choose to download any one of C_TSCM42_64 study guide materials as you like. Just as you know, the PDF version is convenient for you to read and print, since all of the useful study resources for IT exam are included in our SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 exam preparation, we ensure that you can pass the IT exam and get the IT certification successfully with the help of our C_TSCM42_64 practice questions.
No help, full refund
Our company is committed to help all of our customers to pass SAP C_TSCM42_64 as well as obtaining the IT certification successfully, but if you fail exam unfortunately, we will promise you full refund on condition that you show your failed report card to us. In the matter of fact, from the feedbacks of our customers the pass rate has reached 98% to 100%, so you really don't need to worry about that. Our C_TSCM42_64 exam simulation: SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 sell well in many countries and enjoy high reputation in the world market, so you have every reason to believe that our C_TSCM42_64 study guide materials will help you a lot.
We believe that you can tell from our attitudes towards full refund that how confident we are about our products. Therefore, there will be no risk of your property for you to choose our C_TSCM42_64 exam simulation: SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4, and our company will definitely guarantee your success as long as you practice all of the questions in our C_TSCM42_64 study guide materials. Facts speak louder than words, our exam preparations are really worth of your attention, you might as well have a try.
After purchase, Instant Download: Upon successful payment, Our systems will automatically send the product you have purchased to your mailbox by email. (If not received within 12 hours, please contact us. Note: don't forget to check your spam.)
Free demo before buying
We are so proud of high quality of our C_TSCM42_64 exam simulation: SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4, and we would like to invite you to have a try, so please feel free to download the free demo in the website, we firmly believe that you will be attracted by the useful contents in our C_TSCM42_64 study guide materials. There are all essences for the IT exam in our SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 exam questions, which can definitely help you to passed the IT exam and get the IT certification easily.
Under the situation of economic globalization, it is no denying that the competition among all kinds of industries have become increasingly intensified (C_TSCM42_64 exam simulation: SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4), especially the IT industry, there are more and more IT workers all over the world, and the professional knowledge of IT industry is changing with each passing day. Under the circumstances, it is really necessary for you to take part in the SAP C_TSCM42_64 exam and try your best to get the IT certification, but there are only a few study materials for the IT exam, which makes the exam much harder for IT workers. Now, here comes the good news for you. Our company has committed to compile the C_TSCM42_64 study guide materials for IT workers during the 10 years, and we have achieved a lot, we are happy to share our fruits with you in here.
SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP4 Sample Questions:
1. What are the consequences of a confirmation of an operation? (Choose two.)
A) Actual costs are posted for the production confirmed.
B) The operation's capacity requirements are reduced.
C) Serial numbers are assigned for the confirmed quantity.
D) The produced and confirmed quantity is automatically posted to the warehouse stock as a receipt.
2. In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type. What does a firming type define? (Choose two.)
A) Handling existing procurement proposals outside the planning time fence.
B) Handling existing procurement proposals within a planning time fence.
C) Handling new procurement proposals that are to be created due to new requirements within the planning time fence.
D) Handling new requirements within the planning time fence.
3. The company you advise wants to control the availability check in so that when a production and/or process order is created, the following receipts or issues are taken into account: planned orders, purchase orders, production orders, reservations, dependent requirements. When the production and/or process order is released, only the stock that is currently freely usable should be taken into consideration. How can you fulfill this request?
A) Activate the freely usable stock in the scope of check.
B) Enter an appropriate availability checking rule in the order type.
C) Differentiated assignment of two different checking rules in check control.
D) Enter an appropriate availability checking group in the material master.
4. A customer wishes to only produce a finished product when customer orders for it are present. Final assembly should then be carried out at short notice in make-to-order production. Up until this point, the important assemblies needed in final assembly should already be available in stock. Provision of these assemblies should therefore be triggered by planning.
Which options could you offer the customer as useful alternatives in SAP ECC?
(Choose two.)
A) The finished product uses strategy 50 (planning without final assembly) and all the assemblies in the bill of material for the finished product have no strategy.
B) The finished product uses strategy 40 (planning with final assembly) and all the important assemblies in the bill of material for the finished product should have strategy 70 (planning at the assembly level).
C) The finished product uses strategy 20 (make-to-order production) and all the important assemblies in the bill of material for the finished product should have strategy 70 (planning at the assembly level).
D) The finished product uses strategy 30 (production by lots) and all the important assemblies in the bill of material for the finished product should have strategy 70 (planning at the assembly level).
5. Which information is contained in production versions for selecting routings and bills of material?
A) The plant for which the routing and BOM have to be created
B) The routing and BOM alternatives to be used for production
C) All the control parameters for selecting routings and bills of material
D) The explosion date on which the validity of the routing and bill of material is checked
Solutions:
Question # 1 Answer: A,B | Question # 2 Answer: B,C | Question # 3 Answer: C | Question # 4 Answer: A,C | Question # 5 Answer: B |